PROJECT STATUS

IN PROGRESS


_______________________________
PROJECT TIMELINE
FEBRUARY 2019- Preliminary discussion
2020- City contracted engineers for design and construction.
2022- Finalized construction design.

FALL 2022- Submitted for grant funding. Funding denied.

►WINTER 2022-CURRENT - Submitted loan application for funding.

FALL 2024 - Project Advertised for BIDS. 

TBD- Construction Award.
TBD- Construction Planned.
 

Last Updated: 08/29/24.

-Community Development-

Project Contact: Brandon Seitz       Financial Contact: Melissa Ince

DESCRIPTION

The city is in the process of designing and constructing an all-new City sewer services pipeline to the Power City area down Lind Road and behind the Port of Entry off Brownell Road. This is part of an overall utility project to construct the pipeline in 2023.

Why it's needed-Between both communities, a total of 49 new connections will be served by the system being designed. The communities of Brownell and Power City are made up of low income persons with individual septic systems.  The residential members of these communities have discussed connection to the City of Umatilla's wastewater system to increase reliability for the property owners and remove the maintenance responsibilities associated with private septic tanks.

FINANCIAL

BUDGET
Project Budget: $11,362,500.00    
Expenditure to Date: $238,178.00
Total Cost: TBD                                 
FUNDING SOURCES
Community Development Block Grant $2,137,500.00 (est.)
Loan $9,177,805.00
City Funds  $362,500.00                                                  

 

ENGAGEMENT

None.

IMAGES

See below.

 

 

 

Click any thumbnail image to view a slideshow

Brownell Area Project Map
Power City Area Project Map