Nugent Boat Ramp & Lower Parking Improvements

 

PROJECT STATUS

DESIGN & PERMITTING PHASE


_______________________________
PROJECT TIMELINE
FEBRUARY 2019- City staff working with FEMA.
2020- FEMA Coordination.
2021- Contracted for design and construction documents.

2022- Coordination with FEMA.

SPRING 2023- Awaiting grant response.
FALL - SPRING 2024 - Design and Permitting under review.
SPRING 2026 - Construction begins. 
 

Last Updated: 01/24/2025.

-Public Works-

Project Contact: Scott Coleman       

DESCRIPTION

Replacement of damaged boat ramp from flooding event in 2019/2020. Adding docks in day use area and a non-motorized boat launch area. Parking lot improvements include striping to the lower parking area for boat and trailer traffic. 

Why it's needed-This project is mainly to repair damages done from flooding, but also to give residents and locals a different option to launch other than the Columbia River. This location is mainly used for non-motorized use. 

FINANCIAL

BUDGET
Project Budget: $1,700,000.00    
Expenditure to Date: $258,532.83
Total Cost: $1,700.000.00                                 
FUNDING SOURCES
FEMA Funds $868,798.00
Insurance Funds Unknown
Business Oregon (Special Public Works Grant Funds) Unknown                                                                                        
City Funds (Loan) Unknown                                                                    